Calculator · Cost and performance
Cost Forecast and EAC Calculator
Four standard estimates at completion side by side, with the efficiency needed to finish within budget.
Enter your own figures in any currency or unit, used consistently. The form opens with a fictional worked example so you can see how it reads. Calculations run in your browser; nothing is sent or stored. It does not connect to any scheduling or cost system.
Calculator How this tool works: inputs, method and limitations
- Purpose
- Show the range of credible outturn costs from current performance, so a reported forecast can be tested against it.
- Intended user
- Cost managers, commercial leads and project directors reviewing a forecast final cost.
- Output
- Each EAC with its variance at completion and the cost efficiency the remaining work would need, plus the overall range.
- How the result is produced
- Calculated.
- PCMS discipline
- Cost management, forecasting and EAC · Volume 3: Reporting and Performance Management
- Learn the method
- Cost control and forecasting (Practitioner pathway)
- Worked example
- The tool opens with a fictional worked example; “Load example” restores it and “Clear” resets every input. Results can be downloaded as CSV or printed.
- Inputs
- Budget at completion (BAC)
- Earned value (EV)
- Actual cost (AC)
- Planned value (PV)
- Optional: a bottom-up estimate to complete (ETC)
- Method
- CPI = EV ÷ AC; SPI = EV ÷ PV.
- EAC = AC + (BAC − EV) if past variance will not recur; BAC ÷ CPI if cost performance continues; AC + (BAC − EV) ÷ (CPI × SPI) if cost and schedule pressure both continue; AC + ETC for a bottom-up estimate.
- VAC = BAC − EAC; TCPI = (BAC − EV) ÷ (target − AC), against BAC and against each EAC.
- Limitations
- Formula EACs extrapolate the past; they do not know about scope change, claims, escalation or known risks.
- A TCPI well above the CPI achieved so far is a warning, not a plan.
- Uses programme totals; packages with very different performance should be forecast separately.
- Suggested actions
- If the reported forecast sits below the formula range, ask what will change in the remaining work.
- Treat a required TCPI more than about 10% above the achieved CPI as needing an explicit recovery case.
- Reconcile the forecast with approved and pending change before reporting it.
- How to read the result
- The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.
- Related
- Expertise: Project Controls · Reference: Earned value standards · Case study: Hudayriyat West programme · 100-Point Framework · Not sure where to start? Decision Centre
Runs in your browser; nothing is sent to a server. A practitioner’s aid, not a certification or a contractual determination. See how the measures combine in the Programme Intelligence Dashboard. All tools →