Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Calculator · Cost and performance

Cost Forecast and EAC Calculator

Four standard estimates at completion side by side, with the efficiency needed to finish within budget.

Enter your own figures in any currency or unit, used consistently. The form opens with a fictional worked example so you can see how it reads. Calculations run in your browser; nothing is sent or stored. It does not connect to any scheduling or cost system.

The re-estimated cost of the remaining work.
The figure in the report you are testing.
Calculator How this tool works: inputs, method and limitations
Purpose
Show the range of credible outturn costs from current performance, so a reported forecast can be tested against it.
Intended user
Cost managers, commercial leads and project directors reviewing a forecast final cost.
Output
Each EAC with its variance at completion and the cost efficiency the remaining work would need, plus the overall range.
How the result is produced
Calculated.
PCMS discipline
Cost management, forecasting and EAC · Volume 3: Reporting and Performance Management
Learn the method
Cost control and forecasting (Practitioner pathway)
Worked example
The tool opens with a fictional worked example; “Load example” restores it and “Clear” resets every input. Results can be downloaded as CSV or printed.
Inputs
  • Budget at completion (BAC)
  • Earned value (EV)
  • Actual cost (AC)
  • Planned value (PV)
  • Optional: a bottom-up estimate to complete (ETC)
Method
  • CPI = EV ÷ AC; SPI = EV ÷ PV.
  • EAC = AC + (BAC − EV) if past variance will not recur; BAC ÷ CPI if cost performance continues; AC + (BAC − EV) ÷ (CPI × SPI) if cost and schedule pressure both continue; AC + ETC for a bottom-up estimate.
  • VAC = BAC − EAC; TCPI = (BAC − EV) ÷ (target − AC), against BAC and against each EAC.
Limitations
  • Formula EACs extrapolate the past; they do not know about scope change, claims, escalation or known risks.
  • A TCPI well above the CPI achieved so far is a warning, not a plan.
  • Uses programme totals; packages with very different performance should be forecast separately.
Suggested actions
  • If the reported forecast sits below the formula range, ask what will change in the remaining work.
  • Treat a required TCPI more than about 10% above the achieved CPI as needing an explicit recovery case.
  • Reconcile the forecast with approved and pending change before reporting it.
How to read the result
The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.