Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Primavera P6 Practical Guides

Schedule Comparison

What changed between two programmes — where problems hide.

What it is

Comparing two schedules — current against baseline, or update to update — to see exactly what changed: dates, durations, logic, and added or deleted activities.

Why it matters

Most control failures and most disputes hide in what changed between versions. P6’s Schedule Comparison (Claim Digger) surfaces it systematically.

In practice

  • Use Claim Digger / Schedule Comparison to diff two schedules rather than eyeballing them.
  • Compare logic changes, added and deleted activities, duration and constraint changes — not just dates.
  • Undisclosed logic changes between updates are a red flag in any review.
  • Retain every issued update — you cannot compare what you did not keep.

Watch for

  • Reviewing only dates and missing silent logic changes.
  • No retained history to compare against.
  • A baseline changed without record, defeating variance analysis.