Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Primavera P6 Practical Guides

Progress Updating

Recording actuals with the discipline the forecast depends on.

What it is

Recording actual dates, percent complete and remaining duration, and advancing the data date to produce the new forecast.

Why it matters

The update is only as good as its discipline. Inconsistent percent-complete types, a wrong data date, or estimated actuals produce an unreliable forecast.

In practice

  • Set the data date correctly first — it is the line between actual and forecast.
  • Choose the percent-complete type deliberately (Duration, Physical, Units) and apply it consistently across the programme.
  • Remaining duration usually drives the forecast, not the percent typed over it — check which is controlling.
  • Enter real actual dates; do not let P6 back-calculate them from percent on the data date.

Watch for

  • Percent complete that does not reconcile with remaining duration.
  • Actual dates falling after the data date.
  • Physical and duration percent mixed across the schedule.