Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Primavera P6 Practical Guides

Schedule Quality Review

Testing a programme before its dates are trusted.

What it is

A structured technical review of a programme against defined criteria — logic, constraints, float, durations and critical path — before its dates carry any weight.

Why it matters

This is the foundation of schedule assurance. A technically weak programme makes everything measured against it unreliable.

In practice

  • The DCMA 14-point checks are the common baseline: logic, leads, lags, relationship types, hard constraints, high and negative float, high duration, invalid dates, resources, missed tasks, the critical-path test, CPLI and BEI.
  • Automate the checks so “good” is objective and repeatable every cycle.
  • Score against a defined standard, not reviewer preference.
  • Quality review is about reliability, not aesthetics.

Watch for

  • Manual review that varies by reviewer and by cycle.
  • Passing DCMA numerically while the critical path still makes no engineering sense.
  • Treating the checklist as the goal rather than a reliable programme.