Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Primavera P6 Practical Guides

Relationship Types

FS, SS, FF, SF and lags — where logic quality lives.

What it is

The four relationship types (Finish-to-Start, Start-to-Start, Finish-to-Finish, Start-to-Finish) plus lag/lead, which define how activities are logically tied.

Why it matters

Relationship type and lag decide the driving path. Sloppy logic — excess SS/FF pairs, long lags, leads — produces an unreliable critical path.

In practice

  • FS is the default and the cleanest; reach for it first.
  • SS and FF are legitimate but heavily overused, which hides the true drivers.
  • Lags are durations with no logic or resource behind them — minimise and justify every one.
  • A driving relationship is the one actually controlling the successor’s early dates.

Watch for

  • Long lags standing in for activities that should exist.
  • SS+FF pairs used to force overlap and distort float.
  • Negative lags (leads) obscuring the real sequence — avoid them.