Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Urban Infrastructure · Abu Dhabi, UAE

Riyadh City Infrastructure Programme

Programme planning across 14 construction and 2 design contracts, leading 12 senior planners on a city-scale Abu Dhabi development.

Programme ControlsPlanningEOTGovernance
Masterplan top view of the Riyadh City Infrastructure Programme in Abu Dhabi Abu Dhabi, UAE · Abu Dhabi Housing Authority · AED 13.47B

Project at a Glance

Location
Abu Dhabi, UAE
Sector
Urban Infrastructure
Value
AED 13.47B
Role
Programme Planning Manager
Delivery
KBR (PMC)
Period
2020 — 2023

The Riyadh City Infrastructure Programme is a city-scale infrastructure development in Abu Dhabi, United Arab Emirates. Covering roughly 8,500 hectares and 14,897 plots, it was delivered for the Abu Dhabi Housing Authority across a portfolio of construction and design contracts. As Programme Planning Manager within the KBR PMC, I directed Employer-side planning across all 16 contracts and led a team of 12 senior planners.

Evidence-led EOT assessment

Common baseline, progress and reporting standards across every contract meant a contractor’s Extension of Time claim could be tested against a reliable record. Following a detailed, evidence-led assessment of a 291-day claim spanning 17 delay events and 9 affected milestones, a 64-day entitlement was determined and subsequently approved. This sat between the Engineer’s 66-day assessment and the independent forensic specialist’s 60-day assessment. 64 days was the final approved determination.

The insight

At programme scale, consistency is the control. When every contract is planned and measured to the same standard, a claim on any one of them can be tested against a reliable, defensible record — which is what turned a 291-day argument into an approved 64-day determination.

This page describes Rishi Javeri's project-controls role within the programme and does not imply sole delivery of the asset. Figures are drawn from Rishi's own record and are subject to confirmation of disclosable scope; no confidential schedules, dashboards or commercially sensitive material are shown. Imagery to be supplied as owned or licensed only.