Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Delay & EOT

What Makes an EOT Claim Defensible?

The gap between days claimed and days awarded is usually a gap in discipline, not entitlement. I have seen a 291-day claim resolve to 64 — because the analysis behind it was built to survive scrutiny.

By Rishi JaveriPublished 21-Jul-26Updated 12-Aug-267 min read

Entitlement follows the critical path

Time is due only for delay that actually pushes out completion. A delay that consumes float without moving the finish generally carries no extension. The first question is never “how many days was the event?” but “did it drive completion, on the programme current at the time?”

It starts with a credible baseline

You cannot measure delay against a programme no one accepts. Realistic logic, a genuine critical path, no manufactured float — much of the work of winning a claim is done long before the event.

The right method, applied consistently

Choose a recognised method for the timing and records, then apply it consistently. The fastest way to weaken a claim is to appear to have picked the method that gives the biggest number.

Cause, effect, concurrency, records

Evidence every day claimed from cause to critical-path effect; assertion is not entitlement. Address concurrency honestly rather than hoping the other side misses it. And serve notices on time with contemporaneous records — a claim reconstructed months later will never be as strong as one built as events unfold.

Rishi JaveriProject Controls & Programme Governance · FCIArb · FIE · PMP · PSP · MCIOB · MAPM