Calculator · Change management
Change Impact Assessment
Cost, completion delay and the approval level for a proposed change.
Enter your own figures in any currency or unit, used consistently. The form opens with a fictional worked example so you can see how it reads. Calculations run in your browser; nothing is sent or stored. It does not connect to any scheduling or cost system.
Calculator How this tool works: inputs, method and limitations
- Purpose
- Give a quick, consistent first view of what a change does to cost and completion, and who must approve it.
- Intended user
- Change managers, cost engineers, planners and project managers screening a change request.
- Output
- Completion delay, float remaining, cost build-up, contingency after the change and the approval level with its reasons.
- How the result is produced
- Calculated.
- PCMS discipline
- Change and configuration management · Volume 1: Governance
- Learn the method
- Commercial and schedule integration (Management pathway)
- Worked example
- The tool opens with a fictional worked example; “Load example” restores it and “Clear” resets every input. Results can be downloaded as CSV or printed.
- Inputs
- Direct cost of the change
- Time effect on the affected activity (days) and that activity’s total float
- Time-related cost per day of completion delay
- Optional disruption allowance (% of direct cost) and remaining contingency
- Approval limits for project manager and programme director
- Method
- Completion delay = time effect − positive float (not below zero). Negative float means the activity already drives late completion, so all of the time effect counts.
- Total = direct cost + disruption allowance + completion delay × time-related daily cost.
- Approval level by total against the limits; any completion delay lifts approval to at least programme director.
- Limitations
- One activity and its float stand in for a full impacted-programme analysis.
- Does not decide entitlement or who bears the cost.
- Suggested actions
- Run a proper fragnet in the programme for any change that reaches completion.
- Record time and cost effects together in the change register.
- How to read the result
- The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.
- Related
- Expertise: Claims and extension of time · Reference: Risk and change standards · Case study: 291 days claimed, 64 approved · 100-Point Framework · Not sure where to start? Decision Centre
Runs in your browser; nothing is sent to a server. A practitioner’s aid, not a certification or a contractual determination. See how the measures combine in the Programme Intelligence Dashboard. All tools →