One Controls Standard, 16 Contracts
Leading the planning function across a city-scale programme — 16 contracts, 12 senior planners, one standard that made the whole programme governable.
At a glance
- Project context
- Riyadh City Infrastructure Programme, Abu Dhabi: AED 13.47B, 14 civil engineering and 2 design contracts.
- Challenge
- Fourteen inconsistent contractor programmes could not be read or governed as one programme.
- Initial condition
- Interfaces between packages, such as drainage waiting on earthworks, existed in reality but not in the schedules.
- Intervention
- One standard for coding, calendars, fragnets, progress measurement and reporting, run on one governance cycle.
- Methodology
- Employer-side programme planning across all 16 contracts, delivered through a team of 12 senior planners.
- Results
- Comparable information across every contract and a reconciled master programme of more than 15,000 activities.
- Professional contribution
- Programme Planning Manager within the KBR PMC: directing employer-side planning across the 16 contracts and leading the 12 senior planners.
- Lessons learned
- At programme scale, consistency is itself a control.
- Tools and methods
- Interface Management Tracker · Project Controls Setup Check
01 — The Position
A major urban-infrastructure programme in Abu Dhabi — AED 13.47B, delivered through 16 contracts (fourteen civil-engineering packages covering roads, drainage, utility diversions and landscaping, plus two design contracts). The role: Employer-side Programme Planning Manager, accountable for the integrated master programme — the definitive view of where the programme stood at any point — and leading a planning function of twelve senior planners. The starting condition was not ideal.
02 — The Evidence
Fourteen contractor baseline schedules already existed — but each had been developed independently, in different software, with different coding conventions and different levels of scheduling logic. None of them integrated cleanly, and the relationships between adjacent packages — where one contractor’s work created a dependency for another’s — were not captured anywhere. Confidential project records limit the level of detail that can be published.
03 — The Programme Analysis
The core finding was not that any one baseline was poor — it was that inconsistency made the fourteen impossible to read, or govern, as one programme. The interfaces that actually drive an infrastructure programme — the points where drainage waits on earthworks, or a road reinstatement waits on a utility diversion — existed in reality but in none of the schedules.
04 — Event Mapping
Imposing a common standard, package by package: technical alignment sessions with each contractor’s planning team; a shared fragnet library — standardized sub-network templates for recurring work such as sewer connections, substation commissioning and road reinstatement — that every contractor was required to use; and an integrated master programme of more than 15,000 activities that reflected how the work would actually be sequenced across the contracts.
05 — Cause & Effect
Consistent logic across packages did two things at once: it made the master programme defensible, and it sharply cut the time spent arguing about methodology when delays later arose. Inconsistency is not just untidy — it is what makes a programme ungovernable and every subsequent claim contestable. The fragnet library meant a delay was measured the same way whichever contract it arose on.
06 — Critical Path
With a common standard and the interfaces finally captured, the programme had, for the first time, a reliable cross-contract view of what was driving delivery — and risks that were not yet critical, such as interface date conflicts and utility-authority approval sequences running behind, could be seen and escalated before they became critical. On several occasions those escalations led to client decisions that brought forward approvals or resequenced work, avoiding weeks of delay on critical-path activities.
07 — Entitlement / Assessment
The assessment was that the programme needed one controls standard and one governance rhythm — a consolidated performance report to the client’s leadership within 72 hours of each data cut-off, a programme risk register, and a monthly steering committee — all without eliminating the professional judgement of each contractor’s planning team.
08 — The Decision
Impose the common standard — coding, calendars, the fragnet library, progress measurement and reporting — and run the whole programme on one governance cycle across all 16 contracts, led through the twelve senior planners.
09 — The Outcome
Comparable information across every contract; a reconciled master programme of 15,000-plus activities standing as the definitive view; interfaces captured and risks escalated early enough to act on; and one governable programme environment where there had been fourteen disconnected schedules.
10 — Director’s Lesson
At programme scale, consistency is itself a control. Governance does not require eliminating judgement — it requires a common standard, so that judgement can be compared, interfaces can be seen, and a delay becomes a question the programme can answer rather than argue about.
Apply this to your programme
Running many contracts as one programme? Start by checking:
- Do all contracts share one coding, calendar and fragnet standard?
- Are the interfaces between packages captured anywhere?
- Can you roll status up into one comparable programme picture?
- Does exposure reach the decision-maker while there is still time?
Then put it to work: Project Controls Setup Checklist · Programme Governance · Maturity Model · Playbook — Programme Governance.
Follow the thread
Case study → method → evidence → decision: Programme Governance · Decision Intelligence · 291 → 64 on this programme · Director’s Playbook. See the decision framework behind it in How I Work.
This case study describes Rishi Javeri's professional project-controls role and methodology; it does not disclose confidential parties, contracts, schedules or commercially sensitive material, and does not imply sole delivery of the programme. It describes professional practice, not legal advice.