Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Project Controls Leadership

One Controls Standard, 16 Contracts

16 → 1 contracts · unified to one controls standard

Leading the planning function across a city-scale programme — 16 contracts, 12 senior planners, one standard that made the whole programme governable.

At a glance

Project context
Riyadh City Infrastructure Programme, Abu Dhabi: AED 13.47B, 14 civil engineering and 2 design contracts.
Challenge
Fourteen inconsistent contractor programmes could not be read or governed as one programme.
Initial condition
Interfaces between packages, such as drainage waiting on earthworks, existed in reality but not in the schedules.
Intervention
One standard for coding, calendars, fragnets, progress measurement and reporting, run on one governance cycle.
Methodology
Employer-side programme planning across all 16 contracts, delivered through a team of 12 senior planners.
Results
Comparable information across every contract and a reconciled master programme of more than 15,000 activities.
Professional contribution
Programme Planning Manager within the KBR PMC: directing employer-side planning across the 16 contracts and leading the 12 senior planners.
Lessons learned
At programme scale, consistency is itself a control.
Tools and methods
Interface Management Tracker · Project Controls Setup Check

01 — The Position

A major urban-infrastructure programme in Abu Dhabi — AED 13.47B, delivered through 16 contracts (fourteen civil-engineering packages covering roads, drainage, utility diversions and landscaping, plus two design contracts). The role: Employer-side Programme Planning Manager, accountable for the integrated master programme — the definitive view of where the programme stood at any point — and leading a planning function of twelve senior planners. The starting condition was not ideal.

02 — The Evidence

Fourteen contractor baseline schedules already existed — but each had been developed independently, in different software, with different coding conventions and different levels of scheduling logic. None of them integrated cleanly, and the relationships between adjacent packages — where one contractor’s work created a dependency for another’s — were not captured anywhere. Confidential project records limit the level of detail that can be published.

03 — The Programme Analysis

The core finding was not that any one baseline was poor — it was that inconsistency made the fourteen impossible to read, or govern, as one programme. The interfaces that actually drive an infrastructure programme — the points where drainage waits on earthworks, or a road reinstatement waits on a utility diversion — existed in reality but in none of the schedules.

16
contracts, 14 ways of working
→
Common standard
coding · fragnet library
→
15,000+
activities, one master programme
→
1
governable programme
Sixteen contracts and fourteen independently-built baselines brought onto one scheduling standard — a shared fragnet library and coding convention — and integrated into a single master programme of more than 15,000 activities.

04 — Event Mapping

Imposing a common standard, package by package: technical alignment sessions with each contractor’s planning team; a shared fragnet library — standardized sub-network templates for recurring work such as sewer connections, substation commissioning and road reinstatement — that every contractor was required to use; and an integrated master programme of more than 15,000 activities that reflected how the work would actually be sequenced across the contracts.

05 — Cause & Effect

Consistent logic across packages did two things at once: it made the master programme defensible, and it sharply cut the time spent arguing about methodology when delays later arose. Inconsistency is not just untidy — it is what makes a programme ungovernable and every subsequent claim contestable. The fragnet library meant a delay was measured the same way whichever contract it arose on.

06 — Critical Path

With a common standard and the interfaces finally captured, the programme had, for the first time, a reliable cross-contract view of what was driving delivery — and risks that were not yet critical, such as interface date conflicts and utility-authority approval sequences running behind, could be seen and escalated before they became critical. On several occasions those escalations led to client decisions that brought forward approvals or resequenced work, avoiding weeks of delay on critical-path activities.

07 — Entitlement / Assessment

The assessment was that the programme needed one controls standard and one governance rhythm — a consolidated performance report to the client’s leadership within 72 hours of each data cut-off, a programme risk register, and a monthly steering committee — all without eliminating the professional judgement of each contractor’s planning team.

08 — The Decision

Impose the common standard — coding, calendars, the fragnet library, progress measurement and reporting — and run the whole programme on one governance cycle across all 16 contracts, led through the twelve senior planners.

09 — The Outcome

Comparable information across every contract; a reconciled master programme of 15,000-plus activities standing as the definitive view; interfaces captured and risks escalated early enough to act on; and one governable programme environment where there had been fourteen disconnected schedules.

10 — Director’s Lesson

At programme scale, consistency is itself a control. Governance does not require eliminating judgement — it requires a common standard, so that judgement can be compared, interfaces can be seen, and a delay becomes a question the programme can answer rather than argue about.

Apply this to your programme

Running many contracts as one programme? Start by checking:

  • Do all contracts share one coding, calendar and fragnet standard?
  • Are the interfaces between packages captured anywhere?
  • Can you roll status up into one comparable programme picture?
  • Does exposure reach the decision-maker while there is still time?

Then put it to work: Project Controls Setup Checklist · Programme Governance · Maturity Model · Playbook — Programme Governance.

Follow the thread

Case study → method → evidence → decision: Programme Governance · Decision Intelligence · 291 → 64 on this programme · Director’s Playbook. See the decision framework behind it in How I Work.

Author
Rishi Javeri · Project Controls & Programme Governance · FCIArb | FIE | PMP | PSP | MCIOB | MAPM

This case study describes Rishi Javeri's professional project-controls role and methodology; it does not disclose confidential parties, contracts, schedules or commercially sensitive material, and does not imply sole delivery of the programme. It describes professional practice, not legal advice.

Next step

This case applies the Project Controls Management System across many contracts.

A related question? Discuss a professional enquiry, after reading How I Work.