Calculator · Planning and schedule control
Float Consumption Analyser
How fast float is being used on the paths you care about, and which will reach zero first.
Enter your own figures in any currency or unit, used consistently. The form opens with a fictional worked example so you can see how it reads. Calculations run in your browser; nothing is sent or stored. It does not connect to any scheduling or cost system.
Calculator How this tool works: inputs, method and limitations
- Purpose
- Compare total float between two programme updates and show the rate at which it is being consumed.
- Intended user
- Planners and schedule reviewers tracking key milestones and near-critical paths between updates.
- Output
- A row-by-row table with status and periods to zero, counts by status, the erosion share and the first item expected to become critical.
- How the result is produced
- Calculated.
- PCMS discipline
- Planning and scheduling · Volume 2: Planning, Scheduling and Progress Management
- Learn the method
- Planning and scheduling fundamentals (Foundation pathway)
- Worked example
- The tool opens with a fictional worked example; “Load example” restores it and “Clear” resets every input. Results can be downloaded as CSV or printed.
- Inputs
- A list of activities or milestones, each with total float at an earlier update and now (working days)
- Number of reporting periods between the two data dates
- Near-critical threshold in days (default 10)
- Method
- Float consumed = earlier float − current float; rate = consumed ÷ periods elapsed.
- Periods to zero = current float ÷ rate, where float is positive and being consumed.
- Status: negative float, critical (0), near-critical (at or below the threshold) or float available.
- Erosion = float consumed across all rows ÷ total positive float at the earlier update.
- Limitations
- Float changes for many reasons (logic edits, calendars, constraints, re-baselining), not only slow progress; check the cause before drawing conclusions.
- Linear projection assumes the recent rate continues.
- Total float depends on how the programme calculates it (longest path, constraints, multiple float paths).
- Suggested actions
- Ask for the reason behind every large float loss before accepting the update.
- Put items projected to reach zero within two periods on the management watch-list.
- Compare float loss with logic and constraint changes in the update.
- How to read the result
- The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.