Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Construction Claims

FIDIC Extension of Time Claims

Under FIDIC, a strong Extension of Time claim is won as much on procedure as on merit. Miss the notice, and even a genuine delay can fall away.

By Rishi JaveriPublished 16-Aug-266 min read

FIDIC and time

The FIDIC suite of contracts is among the most widely used internationally, including across the UAE and wider GCC. Its clauses set out both the events that entitle a contractor to an Extension of Time and the procedure that must be followed to secure one. Understanding both halves — entitlement and procedure — is what separates a claim that succeeds from one that is technically correct but procedurally lost.

Notice comes first

FIDIC forms are known for their notice and time-bar provisions: a claim must generally be notified within a defined period of the contractor becoming aware of the event. This is the single most common way a meritorious claim fails — not because the delay wasn’t real, but because it wasn’t notified in time. Good contract administration treats notices as part of the claim, not paperwork.

Entitlement follows the critical path

Once procedure is satisfied, entitlement is a delay-analysis question: did the event delay completion, traced along the critical path of the programme current at the time? FIDIC does not change that logic — it is assessed with the same Time Impact Analysis and forensic methods as any other EOT claim, and with the same honesty about concurrent delay.

Records, again

FIDIC’s emphasis on programmes, progress reporting and records is not bureaucracy — it is the evidence base a claim stands on. The contractor who keeps a proper contemporaneous record is the one whose claim survives assessment, as the discipline in how to assess an EOT claim shows from the reviewer’s side.

This is a general explanation of professional practice under standard-form contracts, not legal advice or an interpretation of any specific FIDIC edition.


Go deeper: for entitlement, float and the money question, read Extension of Time — Beyond the Basics.

Rishi JaveriProject Controls & Programme Governance · FCIArb · FIE · PMP · PSP · MCIOB · MAPM