Calculator · Risk management
Risk Exposure Calculator
Three-point cost and time ranges turned into expected exposure, tested against contingency.
Enter your own figures in any currency or unit, used consistently. The form opens with a fictional worked example so you can see how it reads. Calculations run in your browser; nothing is sent or stored. It does not connect to any scheduling or cost system.
Calculator How this tool works: inputs, method and limitations
- Purpose
- Check whether contingency covers the expected exposure from a set of quantified risks.
- Intended user
- Risk managers, cost managers and project directors setting or testing contingency.
- Output
- Expected cost and time exposure by risk and in total, the “if all happen” maximum, the share of the largest risk, and where contingency sits.
- How the result is produced
- Calculated from estimated ranges. Results depend on ratings or estimates you enter; they are not measured performance.
- PCMS discipline
- Risk and opportunity management · Volume 3: Reporting and Performance Management
- Learn the method
- Reading a schedule risk analysis (Advanced pathway)
- Worked example
- The tool opens with a fictional worked example; “Load example” restores it and “Clear” resets every input. Results can be downloaded as CSV or printed.
- Inputs
- Each risk: probability (%), minimum, most likely and maximum cost, and the same for time (days)
- Cost and time contingency (optional)
- Method
- Mean impact = (minimum + 4 × most likely + maximum) ÷ 6 (the PERT weighting).
- Expected exposure = probability × mean impact; totals summed across risks.
- Contingency compared with total expected exposure and with the sum of maximums.
- Limitations
- Expected value, not a simulation: no confidence levels such as P80.
- Time exposures are summed, which overstates when risks sit on parallel paths.
- Assumes risks are independent.
- Suggested actions
- If contingency is below expected exposure, record who carries the gap.
- Where one risk dominates, manage it directly rather than through contingency.
- How to read the result
- The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.
- Related
- Expertise: Project Controls · Reference: Risk and change standards · Case study: Hudayriyat West programme · 100-Point Framework · Not sure where to start? Decision Centre
Runs in your browser; nothing is sent to a server. A practitioner’s aid, not a certification or a contractual determination. See how the measures combine in the Programme Intelligence Dashboard. All tools →