Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Delay Analysis

AACE 29R-03 in Practice

AACE International's Recommended Practice 29R-03 is the most widely cited framework for classifying forensic schedule analysis methods. It doesn't pick a method for you — it gives a common language for choosing one you can defend.

By Rishi JaveriPublished 15-Aug-266 min read

What 29R-03 is

Recommended Practice 29R-03, published by AACE International, is a reference framework for forensic schedule analysis — the retrospective study of programmes and records to establish delay. It is widely respected in the industry as a way to classify and describe methods consistently. It is a guide to method selection and terminology, not a rulebook, and referencing it describes an approach rather than implying any official endorsement.

The method taxonomy

29R-03’s main contribution is a structured taxonomy of methods, organised by two key distinctions:

  • Observational vs modelled — does the analysis observe what the records show (e.g. as-planned vs as-built), or model the effect of events (e.g. impacted as-planned, time impact analysis)?
  • Prospective vs retrospective — is the impact judged as it would have appeared at the time, or reconstructed with hindsight?

From these axes it describes recognised method “MIPs” (method implementation protocols) that practitioners can name precisely rather than argue about loosely.

Why the taxonomy matters

When two experts disagree, they often disagree because they used different methods without saying so. A shared taxonomy forces clarity: which method, applied how, to which records. That transparency is exactly what makes a forensic opinion credible — and reproducible.

Using it in practice

In real work, 29R-03 helps justify why a particular method was chosen for the timing and records at hand — for example, why Time Impact Analysis suited one situation and a windows approach another. Paired with the SCL Protocol, it underpins the disciplined delay analysis behind a defensible EOT position.

This is a general explanation of a professional framework, not legal advice or an official interpretation of AACE materials.