Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Checklist

Monthly Reporting Checklist

Purpose

Make sure a monthly programme report says what leadership actually needs — status, exposure and the decision required.

Who it’s for

Planners and controls managers preparing monthly reports.

When to use it

Every reporting cycle, before the report is issued.

Key areas covered
  • Progress & data-date discipline
  • Critical path & forecast
  • Risk & change
  • Decisions & actions
Related framework Decision Intelligence →
Download PDF ↓ // Tick items on screen for your own review

A report exists to drive a decision, not to prove that work happened.

Headline & decisions

  • One-line status and the trend since last period
  • The decisions required this period, stated up front

Time

  • Progress against baseline (planned vs actual)
  • Current critical path and how it has changed
  • Forecast completion, with its basis

Cost & change

  • Cost position and forecast (with EVM indices where used)
  • Change status — approved, pending and potential

Risk, claims & actions

  • Top risks with owners and movement since last period
  • EOT and claims status, without contractual overstatement
  • Actions with owners and dates; last period’s actions closed out

Discipline

  • Figures reconcile with the schedule and cost systems
  • Bad news is early and plainly stated, not buried