Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Checklist

Recovery Programme Review Checklist

Purpose

Test whether a contractor's recovery programme is credible before you accept it as the new plan — because a cosmetic one just buries the slippage.

Who it’s for

Employer / PMC project controls, planners and PMs reviewing a recovery submission.

When to use it

When a contractor issues a recovery or acceleration programme.

Key areas covered
  • Logic & sequencing
  • Durations & method
  • Resources
  • Constraints & calendars
  • Critical path & float
  • Achievability
Related framework Forecast Integrity →
Download PDF ↓ // Tick items on screen for your own review

Test whether a recovery programme is a genuine, resourced plan — or dates pulled left. Work down the list before you let the new dates change how the job is run.

Logic & sequencing

  • Has logic been relaxed to make the date (FS → SS, overlaps that can’t physically overlap)?
  • Are there negative lags or leads introduced purely to compress the path?
  • Does the recovered sequence still make engineering sense?

Durations & method

  • Where durations are shortened, is there a method statement or basis behind the change?
  • Has anything real changed (crew, shift, plant) to justify a shorter duration?

Resources

  • Is the resource histogram behind the recovery achievable — and ever achieved on this job?
  • Are the assumed labour, plant and long-lead materials actually secured?

Constraints & calendars

  • Is the recovery date held by real logic, or by a constraint on the completion milestone?
  • Do added weekend/night calendars reflect real, resourced, permitted working?

Critical path & float

  • Does the recovered critical path make sense, or now run through improbable activities?
  • Has all float been stripped, leaving no room for the next problem?

Achievability

  • Is there evidence this rate of recovery is achievable, given actuals to date?
  • Does the recovery assume a higher productivity than was achieved when things were going well?