Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Quick Reference

SCL Protocol 2017 — Project Controls Quick Reference

Purpose

Keep the Protocol's working ideas — methods, concurrency, float, time vs money, evidence — in front of the team on a live project.

Who it’s for

Planners, claims teams, contract administrators and project managers.

When to use it

When preparing or reviewing an EOT, choosing an analysis method, or briefing a team on delay.

Key areas covered
  • Delay vs disruption
  • The six analysis methods
  • Concurrency (CP10 / CP14)
  • Float, EOT & compensation
  • Evidence & programme checks
Related framework The SCL Protocol, in Practice →
Download PDF ↓

A one-page working aid to the SCL Delay and Disruption Protocol (2nd Edition, 2017) — the ideas, methods and checks you reach for on a live project. It is a learning aid, not legal advice and not a substitute for the Protocol, your contract or the governing law. Core Principle (CP) references are indicative.

The full explanations sit in the 24-part series, The SCL Protocol, in Practice.

Key concepts

  • The Protocol is guidance, not law. The contract, governing law, facts and evidence decide entitlement.
  • Delay = critical delay to completion (a time question → EOT).
  • Disruption = loss of productivity (a money question; independent of the finish date).
  • Critical path = the longest path driving completion; least float. It shifts over time.
  • Float = spare time before a path affects completion (total float) or its successor (free float).
  • Baseline = the agreed starting line; must be realistic, logic-driven and (ideally) accepted.
  • Assess contemporaneously — don’t “wait and see”. (CP4)

Delay terminology

  • Employer / Contractor Risk Event — who bears the risk under the contract.
  • EOT — relieves LDs for Employer-risk delay; sets a new completion date; stops time going “at large”. (CP2)
  • Net vs gross — EOT = Employer-risk critical delay, not total slip.
  • Fragnet — a sub-network modelling an event’s impact.
  • Data date — the “as-at” line dividing actual from forecast.
  • Prospective — likely impact from a point in time. Retrospective — actual impact with hindsight.

Six analysis methods (11.5)

  • Impacted As-Planned — events on the baseline; theoretical; least data.
  • Time Impact Analysis — fragnet on the contemporaneous update; forecast; fits “assess as you go”.
  • Time Slice Windows — critical path read per window from updates; needs good updates.
  • As-Planned vs As-Built Windows — plan vs record per window; needs good as-built.
  • Retrospective Longest Path — trace the as-built critical path back from completion.
  • Collapsed As-Built (but-for) — remove events from the as-built; needs imputed logic.
  • No preferred method — choose by records, stage, contract, value, proportionality. (CP11)

Concurrency

  • Not just “two delays at once”. Needs two effective causes of critical delay — one each side — coinciding in time. Rare.
  • Three gates: opposite risk · genuine criticality (no float) · coinciding effects.
  • Time (CP10): Contractor’s concurrent delay should not reduce the EOT due.
  • Money (CP14): generally no prolongation for the concurrent period — unless Employer-caused loss can be separated.
  • Contract & law govern — jurisdictions differ (incl. apportionment).

EOT, float & compensation

  • Float is generally not owned by either party unless the contract says so. (CP8/9)
  • A delay absorbed by float usually gives no EOT.
  • EOT ≠ money. Different doors, different keys. (CP12)
  • Four outcomes: both · time-only · money-only (disruption) · neither.
  • Mitigation (CP15) = reasonable steps, no significant cost. Acceleration (CP16) = cost to finish earlier; instructed = compensable, constructive = difficult.

Evidence checklist (CP1 / App. B)

  • Programme — baseline, updates, revisions
  • Progress — actual start/finish, % complete, as-built
  • Resource — labour, plant, subcontractor, timesheets
  • Cost — reports, applications, valuations
  • Correspondence — RFIs, instructions, notices, minutes, drawing registers
  • Contract & tender documents
  • Keep records contemporaneously — reconstructed narratives are discounted.

Programme checklist

  • Baseline accepted / reviewed under the contract
  • Realistic durations; complete logic; minimal open ends
  • Few constraints — each justified (no mandatory-finish forcing the date)
  • Updates with correct data date and honest actuals
  • Dated snapshots saved; audit trail preserved (never overwrite)
  • Float real, not manufactured; criticality demonstrated, not asserted

Common mistakes

  • Treating “SCL Protocol” as law or as proof of entitlement
  • Confusing delay (time) with disruption (money)
  • Equating total lateness with EOT entitlement
  • Assuming “critical in P6” = critical to the contract completion date
  • Trusting an unaccepted or constraint-propped baseline
  • Picking a method for its number, or one the records can’t support
  • Calling any temporal overlap “concurrency”
  • Assuming EOT brings prolongation money
  • Reading “mitigate” as authority to accelerate and recover cost
  • A global claim used to cover a records failure