SCL Protocol 2017 — Project Controls Quick Reference
Purpose
Keep the Protocol's working ideas — methods, concurrency, float, time vs money, evidence — in front of the team on a live project.
Who it’s for
Planners, claims teams, contract administrators and project managers.
When to use it
When preparing or reviewing an EOT, choosing an analysis method, or briefing a team on delay.
Key areas covered
- Delay vs disruption
- The six analysis methods
- Concurrency (CP10 / CP14)
- Float, EOT & compensation
- Evidence & programme checks
Related framework The SCL Protocol, in Practice →
A one-page working aid to the SCL Delay and Disruption Protocol (2nd Edition, 2017) — the ideas, methods and checks you reach for on a live project. It is a learning aid, not legal advice and not a substitute for the Protocol, your contract or the governing law. Core Principle (CP) references are indicative.
The full explanations sit in the 24-part series, The SCL Protocol, in Practice.
Key concepts
- The Protocol is guidance, not law. The contract, governing law, facts and evidence decide entitlement.
- Delay = critical delay to completion (a time question → EOT).
- Disruption = loss of productivity (a money question; independent of the finish date).
- Critical path = the longest path driving completion; least float. It shifts over time.
- Float = spare time before a path affects completion (total float) or its successor (free float).
- Baseline = the agreed starting line; must be realistic, logic-driven and (ideally) accepted.
- Assess contemporaneously — don’t “wait and see”. (CP4)
Delay terminology
- Employer / Contractor Risk Event — who bears the risk under the contract.
- EOT — relieves LDs for Employer-risk delay; sets a new completion date; stops time going “at large”. (CP2)
- Net vs gross — EOT = Employer-risk critical delay, not total slip.
- Fragnet — a sub-network modelling an event’s impact.
- Data date — the “as-at” line dividing actual from forecast.
- Prospective — likely impact from a point in time. Retrospective — actual impact with hindsight.
Six analysis methods (11.5)
- Impacted As-Planned — events on the baseline; theoretical; least data.
- Time Impact Analysis — fragnet on the contemporaneous update; forecast; fits “assess as you go”.
- Time Slice Windows — critical path read per window from updates; needs good updates.
- As-Planned vs As-Built Windows — plan vs record per window; needs good as-built.
- Retrospective Longest Path — trace the as-built critical path back from completion.
- Collapsed As-Built (but-for) — remove events from the as-built; needs imputed logic.
- No preferred method — choose by records, stage, contract, value, proportionality. (CP11)
Concurrency
- Not just “two delays at once”. Needs two effective causes of critical delay — one each side — coinciding in time. Rare.
- Three gates: opposite risk · genuine criticality (no float) · coinciding effects.
- Time (CP10): Contractor’s concurrent delay should not reduce the EOT due.
- Money (CP14): generally no prolongation for the concurrent period — unless Employer-caused loss can be separated.
- Contract & law govern — jurisdictions differ (incl. apportionment).
EOT, float & compensation
- Float is generally not owned by either party unless the contract says so. (CP8/9)
- A delay absorbed by float usually gives no EOT.
- EOT ≠ money. Different doors, different keys. (CP12)
- Four outcomes: both · time-only · money-only (disruption) · neither.
- Mitigation (CP15) = reasonable steps, no significant cost. Acceleration (CP16) = cost to finish earlier; instructed = compensable, constructive = difficult.
Evidence checklist (CP1 / App. B)
- Programme — baseline, updates, revisions
- Progress — actual start/finish, % complete, as-built
- Resource — labour, plant, subcontractor, timesheets
- Cost — reports, applications, valuations
- Correspondence — RFIs, instructions, notices, minutes, drawing registers
- Contract & tender documents
- Keep records contemporaneously — reconstructed narratives are discounted.
Programme checklist
- Baseline accepted / reviewed under the contract
- Realistic durations; complete logic; minimal open ends
- Few constraints — each justified (no mandatory-finish forcing the date)
- Updates with correct data date and honest actuals
- Dated snapshots saved; audit trail preserved (never overwrite)
- Float real, not manufactured; criticality demonstrated, not asserted
Common mistakes
- Treating “SCL Protocol” as law or as proof of entitlement
- Confusing delay (time) with disruption (money)
- Equating total lateness with EOT entitlement
- Assuming “critical in P6” = critical to the contract completion date
- Trusting an unaccepted or constraint-propped baseline
- Picking a method for its number, or one the records can’t support
- Calling any temporal overlap “concurrency”
- Assuming EOT brings prolongation money
- Reading “mitigate” as authority to accelerate and recover cost
- A global claim used to cover a records failure