Delay Analysis
The SCL Protocol, in Practice · Part 10 of 24
The Six Methods at a Glance
The Protocol sets out six recognised delay-analysis methods — and, in the 2nd Edition, deliberately stops telling you which to use for analysis done long after the event. Instead it gives you the dimensions that separate them: the direction of the analysis, how the critical path is found, and whether you're forecasting or looking back. Learn the map, and the individual methods stop being a soup of acronyms.
The Protocol sets out six recognised delay-analysis methods — and, in the 2nd Edition, deliberately stops telling you which to use for analysis done long after the event. Instead it gives you the dimensions that separate them: the direction of the analysis, how the critical path is found, and whether you’re forecasting or looking back. Learn the map, and the individual methods stop being a soup of acronyms.
The construction-site version
Imagine a toolbox with six tools in it. None of them is “the best tool” — a mallet isn’t better than a torque wrench, it’s better for a different job. The mistake isn’t owning six tools; it’s reaching for the one you like regardless of the task, or the one that happens to give the number you want.
The six delay-analysis methods are that toolbox. They differ in what they assume, what data they need, and what question they answer. Knowing the map tells you which is honest to use when.
The technical bit
The Protocol tabulates the six methods and classifies each on a few axes. The two that matter most for getting your bearings: direction — does the analysis run cause → effect (start with the event, model its impact) or effect → cause (start with the actual delay, trace back to its causes)? And how the critical path is established — prospectively (from the plan), contemporaneously (from the programme as it stood at the time), or retrospectively (from the as-built).
The six: Impacted As-Planned and Time Impact Analysis run cause → effect and are modelled (forecast) methods. Time Slice Windows and As-Planned vs As-Built Windows run effect → cause across the contemporaneous critical path, retrospectively. Retrospective Longest Path traces the as-built critical path back from completion. Collapsed As-Built (the “but-for” method) subtracts events from the as-built to see what would have happened without them. The headline change in the 2nd Edition: it no longer declares a preferred method for time-distant analysis. The choice is a matter of fit.
How three roles should read it
Each method demands different data. Modelled methods (Impacted As-Planned, Time Impact Analysis) need good logic and clean fragnets; the windows and as-built methods need reliable as-built records. Match the method to the data you actually have, not the one you wish you had.
Expect the method to be scrutinised as hard as the result. Be ready to justify why this method, for this dispute, at this stage, on these records. “It’s the one our expert always uses” is not a reason the other side — or a tribunal — has to accept.
You don’t need to run these, but you should recognise them, because the method chosen can move the number materially. If two experts reach different figures, the method and its assumptions are usually where the difference lives.
The trap
Treating one method as universally “best,” or picking the method that yields the most convenient number. The Protocol removed its preferred method precisely to stop that — the right method is the one that fits the facts, the stage, the purpose and the records.
Same project, same events, two experts. One runs an Impacted As-Planned (theoretical, baseline-only) and gets 25 days. The other runs an As-Planned vs As-Built Windows analysis (grounded in what actually happened) and gets 16 days. Neither is lying. The methods ask different questions of different data. The honest discussion is about which question fits the dispute — not which number is bigger.
What the Protocol says — and doesn’t
It identifies six commonly used methods and tabulates them by analysis type (cause → effect or effect → cause), how the critical path is determined, and how the delay impact is determined. It does not rank them or mandate one for time-distant analysis.
What it does not say:
- That any single method is the correct or preferred one.
- That a more complex method is automatically more reliable.
- That the method can be chosen independently of the records available.
- That the method chosen is beyond challenge — it is routinely contested.
”There’s a correct SCL method — you just need to use it.”
The 2nd Edition sets out six methods and names no favourite for time-distant analysis. The appropriate method depends on the facts, the stage, the purpose and the records.
The method decides what you build in P6: a modelled impact on a baseline (Impacted As-Planned), a fragnet on the contemporaneous update (Time Impact Analysis), a series of dated windows (Time Slice / As-Planned vs As-Built), or an as-built from which events are subtracted (Collapsed As-Built). Pick the method first; it dictates the file.
Evidence check
- An accepted, logic-linked baseline (all methods lean on it)
- Regular programme updates (for contemporaneous/windows methods)
- Reliable as-built records (for windows and as-built methods)
- The event records and fragnet basis (for modelled methods)
Which method is defensible depends on which of these you actually have.
Rishi’s takeaway
- Six methods, two key axes: direction (cause→effect / effect→cause) and how the critical path is found.
- No universal best method — the 2nd Edition removed the preference on purpose.
- The data you have narrows the honest choices more than any preference does.
- When two analyses disagree, look first at the method and its assumptions.
There’s no best delay-analysis method — only the one that fits the facts, the stage and the records you actually kept.
References. Society of Construction Law, Delay and Disruption Protocol, 2nd Edition, February 2017 — guidance on delay analysis, including the six methods tabulated at paragraph 11.5 and the removal of a preferred method for time-distant analysis. Method selection depends on the contract, the stage, the purpose and the records. Educational commentary; not legal advice.
Common questions
What are the six delay analysis methods in the SCL Protocol?
The Protocol sets out six recognised delay-analysis methods — and, in the 2nd Edition, deliberately stops telling you which to use for analysis done long after the event. Instead it gives you the dimensions that separate them: the direction of the analysis, how the critical path is found, and whether you're forecasting or looking back.
Is there a preferred SCL delay analysis method?
The 2nd Edition sets out six methods and names no favourite for time-distant analysis. The appropriate method depends on the facts, the stage, the purpose and the records.
How does the SCL Protocol classify delay analysis methods?
It identifies six commonly used methods and tabulates them by analysis type (cause → effect or effect → cause), how the critical path is determined, and how the delay impact is determined. It does not rank them or mandate one for time-distant analysis.