Module · Programme management
Benefits Realisation Planner
A benefits register with owners, baselines, targets, dependencies and realisation dates, and a tracking view that compares progress achieved with progress expected.
Enter your own figures in any currency or unit, used consistently. The form opens with a fictional worked example so you can see how it reads. Calculations run in your browser; nothing is sent or stored. It does not connect to any scheduling or cost system.
Module How this tool works: inputs, method and limitations
- Purpose
- Plan and track the outcomes a programme exists to deliver, separately from the outputs its projects hand over.
- Intended user
- Programme managers, sponsors, benefit owners and PMO leads.
- Output
- A benefits register with status, a tracking view, a summary by objective, upcoming realisation dates and ownership gaps.
- How the result is produced
- Calculated from figures you enter.
- PCMS discipline
- Programme and project governance · Volume 1: Governance
- Learn the method
- Project controls operating models (Leadership pathway)
- Inputs
- Programme start date and review date
- For each benefit: objective, description, measure, owner, baseline, target, current value, realisation date, dependency, measurement frequency and owner after closure
- Method
- Achieved progress = (current − baseline) ÷ (target − baseline), so falling targets such as journey time work too.
- Expected progress rises in a straight line from the programme start to the realisation date.
- On track when the shortfall is 10 percentage points or less; at risk up to 25; off track beyond 25. Overdue when the date has passed before the target is met.
- Gaps flagged: no owner, no measure, no owner after closure, target equal to baseline, missing dates.
- Limitations
- Straight-line expectation is a simplification; most benefits arrive late in a programme and follow an S-curve.
- It tracks what you enter; it does not measure or verify benefits.
- A self-managed planning aid, not a benefits audit.
- An educational tool: not affiliated with PMI, not accredited training and not exam or certification preparation.
- Suggested actions
- Give every benefit a named owner who will still be there after the programme closes.
- Agree the baseline and how it is measured before work starts.
- Report outcomes separately from project outputs at every programme board.
- How to read the result
- The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.
- Related
- Expertise: Programme Management and Governance · Reference: Programme governance standards · Case study: 16 contracts under one standard · 100-Point Framework · Not sure where to start? Decision Centre
Runs in your browser; nothing is sent to a server. A practitioner’s aid, not a certification or a contractual determination. See how the measures combine in the Programme Intelligence Dashboard. All tools →