Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Primavera P6 Practical Guides

Critical Path Analysis

The path driving completion — and why P6 may report the wrong one.

What it is

The longest chain of dependent activities driving the completion date. In P6, “critical” defaults to total float at or below zero (or a set threshold), which is not always the same as the true longest path.

Why it matters

Time entitlement follows the critical path. The path P6 shows depends on your settings, calendars and constraints — so it has to be validated, not assumed.

In practice

  • Know your definition: Total Float vs Longest Path. They can return different paths.
  • The Longest Path option follows driving relationships to the finish and ignores float thresholds — often the more honest view.
  • Multiple calendars distort total float; check the path still makes sense across calendar boundaries.
  • A single hard constraint can manufacture or mask criticality.

Watch for

  • Trusting “critical = red” without asking why an activity is on the path.
  • A critical path running through a constraint rather than logic.
  • Near-critical (low-float) paths that quietly take over at the next update.