Module · Programme management
Programme Interdependency Mapper
Map the dependencies between component projects and external parties, see which late handovers cascade, and who must act.
Enter your own figures in any currency or unit, used consistently. The form opens with a fictional worked example so you can see how it reads. Calculations run in your browser; nothing is sent or stored. It does not connect to any scheduling or cost system.
Module How this tool works: inputs, method and limitations
- Purpose
- Make cross-component dependencies visible, dated and owned, and show how one late handover moves the components that depend on it.
- Intended user
- Programme directors, PMO leads, interface managers and component project managers.
- Output
- A relationship map, a dependency register with slip and knock-on delay, the cascade, external dependencies and escalations.
- How the result is produced
- Calculated from dates you enter.
- PCMS discipline
- Interface management · Volume 2: Planning, Scheduling and Progress Management
- Learn the method
- One standard across contracts (Controls System) (Management pathway)
- Inputs
- For each dependency: giving and receiving component, what is handed over, type, need date, forecast date, float at the receiver, owner, critical or not
- Method
- Components are sequenced by their dependencies; a loop is reported as an error.
- Slip = forecast plus any delay inherited from the giving component, minus the need date.
- Delay passed on = slip minus the receiver’s float; a component’s delay is the largest delay passed to it.
- Escalate any critical dependency that is late, and any late dependency without an owner.
- Limitations
- Assumes a component’s delay moves its later handovers day for day; recovery, calendars and resources are not modelled.
- Float at the receiver is entered, not calculated; take it from the component schedule.
- A structuring aid, not an integrated master schedule.
- An educational tool: not affiliated with PMI, not accredited training and not exam or certification preparation.
- Suggested actions
- Put every dependency in both parties’ schedules with the same date.
- Escalate late dependencies early in the chain first.
- Engage external parties through the sponsor.
- How to read the result
- The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.
- Related
- Expertise: Programme Management and Governance · Reference: Programme governance standards · Case study: Hudayriyat West programme · 100-Point Framework · Not sure where to start? Decision Centre
Runs in your browser; nothing is sent to a server. A practitioner’s aid, not a certification or a contractual determination. See how the measures combine in the Programme Intelligence Dashboard. All tools →