Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Module · Programme management

Programme Interdependency Mapper

Map the dependencies between component projects and external parties, see which late handovers cascade, and who must act.

Enter your own figures in any currency or unit, used consistently. The form opens with a fictional worked example so you can see how it reads. Calculations run in your browser; nothing is sent or stored. It does not connect to any scheduling or cost system.

Dependencies between components

One row per dependency: the giving component, the receiving component, what is handed over, when it is needed and when it is forecast. Float is the time the receiving component can absorb before its own dates move.

Module How this tool works: inputs, method and limitations
Purpose
Make cross-component dependencies visible, dated and owned, and show how one late handover moves the components that depend on it.
Intended user
Programme directors, PMO leads, interface managers and component project managers.
Output
A relationship map, a dependency register with slip and knock-on delay, the cascade, external dependencies and escalations.
How the result is produced
Calculated from dates you enter.
PCMS discipline
Interface management · Volume 2: Planning, Scheduling and Progress Management
Learn the method
One standard across contracts (Controls System) (Management pathway)
Inputs
  • For each dependency: giving and receiving component, what is handed over, type, need date, forecast date, float at the receiver, owner, critical or not
Method
  • Components are sequenced by their dependencies; a loop is reported as an error.
  • Slip = forecast plus any delay inherited from the giving component, minus the need date.
  • Delay passed on = slip minus the receiver’s float; a component’s delay is the largest delay passed to it.
  • Escalate any critical dependency that is late, and any late dependency without an owner.
Limitations
  • Assumes a component’s delay moves its later handovers day for day; recovery, calendars and resources are not modelled.
  • Float at the receiver is entered, not calculated; take it from the component schedule.
  • A structuring aid, not an integrated master schedule.
  • An educational tool: not affiliated with PMI, not accredited training and not exam or certification preparation.
Suggested actions
  • Put every dependency in both parties’ schedules with the same date.
  • Escalate late dependencies early in the chain first.
  • Engage external parties through the sponsor.
How to read the result
The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.