Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Hospitality & Mixed-Use · Dubai, UAE

Ibn Battuta Gate Hotel & Offices

Lead planning and controls on a mixed-use landmark, including baseline management and recovery programmes.

PlanningRecoveryReporting
Night panorama of Ibn Battuta Gate, Dubai, with the illuminated central archway Dubai, UAE · AED 925M

Project at a Glance

Location
Dubai, UAE
Sector
Hospitality & Mixed-Use
Value
AED 925M
Role
Lead Planning Engineer
Delivery
BAM International
Period
2007 — 2010

A landmark mixed-use development in Dubai — a five-star hotel, serviced apartments and offices, together with the Palm Jebel Ali service tunnel.

The controls challenge

Mixed-use programmes combine different building types, fit-out standards and handover requirements under one completion drive. As Lead Planning Engineer with BAM International, I led baseline management, progress measurement, executive reporting and the recovery programmes needed to protect completion when elements came under pressure.

The insight

On mixed-use work, recovery is a recurring discipline, not a one-off event. A recovery plan is only worth the paper it’s on if the sequence and resources are genuinely deliverable.

Project Gallery

This page describes Rishi Javeri's project-controls role within the programme and does not imply sole delivery of the asset. Figures are drawn from Rishi's own record and are subject to confirmation of disclosable scope; no confidential schedules, dashboards or commercially sensitive material are shown. Imagery to be supplied as owned or licensed only.