Module · Programme management
Programme Health and Delivery Confidence
Ten areas of programme health, from strategic alignment and benefits to schedule, cost and dependencies, combined into a stated-rule view of delivery confidence.
Enter your own figures in any currency or unit, used consistently. The form opens with a fictional worked example so you can see how it reads. Calculations run in your browser; nothing is sent or stored. It does not connect to any scheduling or cost system.
Module How this tool works: inputs, method and limitations
- Purpose
- Give a programme board one view of whether the programme is likely to deliver its outcomes, with every rating traceable to a rule.
- Intended user
- Programme directors, sponsors, PMO leads and assurance reviewers.
- Output
- A ten-area health table, the delivery confidence rating with its rule, and the assumptions behind it.
- How the result is produced
- Rule-based, partly from judgement-based ratings. Results depend on ratings or estimates you enter; they are not measured performance.
- PCMS discipline
- Reporting, dashboards and decision intelligence · Volume 3: Reporting and Performance Management
- Learn the method
- What senior management actually needs (Foundation pathway)
- Inputs
- Ratings 1 to 5 for strategic alignment, governance, stakeholders and resources
- Benefits on track (%), forecast delay and SPI(t), EAC variance and CPI, risks above threshold, component projects rated red, critical interfaces overdue
- Method
- Measured areas use the platform’s common RAG thresholds.
- Ratings of 4–5 are green, 3 amber and 1–2 red; they are marked as judgement.
- Delivery confidence is red if strategic alignment, benefits, schedule or cost is red, or three areas are red; amber if any area is red, three are amber or a key area is amber; otherwise green. At least six areas must be rated.
- Limitations
- Self-assessed and rule-based; not the UK government’s Delivery Confidence Assessment or any other official method.
- Judgement ratings are not measured performance.
- The rules are reading aids; adapt them to your governance.
- An educational tool: not affiliated with PMI, not accredited training and not exam or certification preparation.
- Suggested actions
- Rate the judgement areas as a board, not alone.
- Explain every red with an action and an owner.
- Re-assess at each stage gate.
- How to read the result
- The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.
- Related
- Expertise: Digital Project Controls · Reference: Programme governance standards · Case study: Hudayriyat West programme · 100-Point Framework · Not sure where to start? Decision Centre
Runs in your browser; nothing is sent to a server. A practitioner’s aid, not a certification or a contractual determination. See how the measures combine in the Programme Intelligence Dashboard. All tools →