Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Schedule Assurance

Why Recovery Programmes Fail

A recovery programme is a promise to leadership that lost time will be regained. Most break that promise — not because recovery was impossible, but because the plan was never actually deliverable.

By Rishi JaveriPublished 08-Aug-26Updated 12-Aug-266 min read

Compression is not recovery

The commonest failure is cosmetic: durations squeezed and bars overlapped until the finish date returns to plan, with nothing in the real world changed to justify it. If the resources, sequence and constraints are identical, a shorter programme is not a recovery — it is the same delay, hidden.

The constraints that caused the delay are still there

A credible recovery names the cause and changes something about it — more resource, a different sequence, an unblocked approval, a released interface. A plan that leaves every original constraint in place is asking to fail the same way twice.

Optimism compounds

Recovery plans tend to stack best-case assumptions: peak productivity, no weather, instant approvals, perfect logistics. Each is plausible alone; together they are fiction. A recovery that only works if everything goes right will not work.

How to test one

Ask three questions: what specifically has changed since the delay; is the changed sequence physically and contractually buildable; and does the resource histogram the plan implies actually exist? If the answers are vague, the programme is a wish. A real recovery survives those questions — and is worth monitoring weekly against them.

Rishi JaveriProject Controls & Programme Governance · FCIArb · FIE · PMP · PSP · MCIOB · MAPM