Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Primavera P6

Common Primavera P6 Scheduling Mistakes

P6 will faithfully calculate nonsense if you feed it nonsense. The most damaging scheduling mistakes are not exotic — they are ordinary habits that quietly destroy a programme's reliability.

By Rishi JaveriPublished 10-Aug-26Updated 12-Aug-266 min read

Constraints used to force dates

The single most common mistake: applying hard constraints to make activities land on desired dates, overriding the logic. It produces a schedule that looks on-target and tells you nothing when things change. Most constraints should not be there.

Open ends and dangling logic

Activities missing a predecessor or successor break the network so delay no longer flows through it. A programme full of open ends has a critical path that cannot be believed.

Negative lags to fake overlap

Using negative lag to force activities to overlap distorts the network and flatters the finish. Model the real overlap with proper relationships instead.

Durations with no basis

Durations estimated by feel — every activity a round 10 or 20 days — signal a programme built to look complete rather than to be built. Durations should trace to a quantity and a resourcing basis.

Progress that doesn’t reconcile

Updating percent-complete without honest actual dates, or leaving actuals in the future and forecasts in the past, means nothing calculated from the schedule can be trusted. Discipline in the update is as important as discipline in the build.

The fix is a standard

None of these needs genius to catch — they need a consistent quality standard applied every cycle, ideally automated. Run a programme against the schedule health checklist and these mistakes surface before they cost anything.